Construction revenue assurance

Find and recover
every dollar of
additional work.

Out-of-scope work is priced by the people who do it least well: nobody. Change Order Systems detects variations from your drawings, field records and correspondence, builds a defensible notice package in minutes rather than days, and follows every claim from the moment it happens on site to the moment it clears the bank.

Your own workspace, isolated from every other company on the platform. No card required to start.

0%
Target reduction in days from field event to compliant notice
0
Detectors watching field, email, RFIs and drawing revisions
0%
Of claimed amounts traced to a contemporaneous record
Live product view
MSG-2411 · Atrium Tower
MSG-2411-CE-101
Post-tensioned cables found in B3 penetration zone
notice due
Notice clockdue soon
2d 04:19:07
cl 25.27 cal daysLatent condition noticetime bar
Detected to collected · this portfolio
Detected
$310.5k
Documented
$288.8k
Submitted
$288.8k
Approved
$211.8k
Invoiced
$181.5k
Collected
$147.5k
Leaking before submission−$21.6k
Built for specialty subcontractors
ElectricalMechanicalHVACConcreteCivilFire protectionFit-out
20–500 staff · 10+ active projects · material variation leakage
01Where the money goes

Variation revenue does not get rejected. It gets lost.

Almost none of it is lost in an argument. It is lost in the gap between the work happening and anybody writing it down properly — four gaps, specifically, and every one of them is a process problem rather than a legal one.

01Unpriced work in progress

Work starts before anyone prices it

A superintendent says proceed on a walk-through. The crew goes. Hours and materials accrue against a ticket nobody has linked to a claim, and the cost is yours until somebody notices.

02Claims barred by time

The notice period runs out quietly

Most contracts bar a variation claim that is not noticed within a set number of business days of becoming aware. The clock starts on site. It rarely starts in anyone's calendar.

03Weak substantiation

The evidence is scattered by the time it matters

Photographs on one phone, the instruction in somebody's inbox, the dockets in a ute. Assembling a defensible package six months later costs days and still has holes in it.

04Approved but uncollected

Approved work never becomes cash

A variation is agreed, then sits unbilled, or is billed and never chased. The disputed balance quietly becomes the write-off nobody put a name to.

Every one of those four is measured on the recovery board from day one — unpriced work in progress, deadlines about to pass, missing evidence, and approved value that has not turned into cash. You cannot fix a leak you are not looking at.

Start a workspace
02How it works

Five steps, and the platform does the remembering.

It sits alongside your project management and accounting systems rather than replacing them. Nothing here asks a contractor to change how they build — only how the paperwork keeps up.

01

Load the contract and the baseline

Contract, scope, estimate, rate sheet, drawings, programme and notice clauses. Extracted obligations and deadlines stay proposed until a person reviews them, each with a page and region citation back to the source document.

What you get
A versioned scope baseline and a reviewed set of notice rules
02

Capture what happened, on site, at the time

Voice, text, photographs, video and location from a phone that works without signal. Timestamp and device metadata are captured at the moment of the event, not at the moment of sync. A foreperson validates and attaches labour, plant and material.

What you get
A contemporaneous record that stands up later
03

Let the engine find the variation

Field records, correspondence, RFIs, drawing revisions and daily logs are continuously compared against the baseline. Anything that no scope item covers becomes a signal with its sources cited, its confidence broken down, and the evidence it is missing named.

What you get
A triage queue instead of a memory test
04

Price it and serve the notice

Cost builds from the quantities already recorded, against the agreed schedule of rates, with every line showing where its number came from. The notice is generated from a controlled template, previewed with its recipients, and served only when an authorised person approves it.

What you get
Minutes to a compliant, priced notice
05

Track it to cash

The client reviews an exact version through a portal that never sees your cost or margin. Partial approvals, comments and signatures land on the record. Approved amounts sync to accounting; payments reconcile; the disputed balance keeps a next action and an owner.

What you get
A funnel from signal to bank, not a folder
03The signature capability

A notice deadline is arithmetic.
So we made it run like a clock.

Most contracts bar a variation claim that is not noticed within a set period of becoming aware. That period is not a reminder or a best guess — it is a calculation over a specific clause, a specific contract version and a specific working calendar. Treating it as anything softer is how claims get barred.

01

Rules are read from your contract, then reviewed

Clause extraction proposes the notice type, the trigger, the period, the recipients and the delivery method, each citing the page and region it came from. A rule built on an unapproved clause cannot start a clock.

02

The clock starts when a person confirms the classification

The engine never starts it on its own. Once a project manager confirms what kind of contractual event this is, the deadline is fixed arithmetic — no model, no heuristic.

03

The calendar is frozen with the notice

Weekends, public holidays and the business-day basis travel with the record. A deadline computed under contract version 1 still recomputes correctly after a deed of variation shortens the period.

04

It escalates before it fails, not after

Warning, critical and breached states surface on the board, in the register and on the notice screen — with the exposure in dollars next to each one, so triage is by money at risk rather than by whoever shouted last.

What a barred claim costs

A subcontractor who misses a ten business day notice period on a $40,000 variation has not lost a percentage of it. They have lost the entitlement to claim it at all, along with the margin that was supposed to sit inside it — and the labour and material have already been spent.

Cost already incurred
$35,700
Margin foregone
$4,300
Recoverable after the bar
$0
Recoverable with a served notice
$40,000

Illustrative figures on a single mid-sized variation. Whether a claim is in fact barred is a contractual question for your commercial manager and your advisers — the platform records the position taken and the date it was taken, it does not determine entitlement.

04Against what you already looked at

Parity where it is table stakes. Difference where it matters.

Clearstory, Buildertrend and Buildxact are all real products that do real work. Here is an honest read of where we match them, where we go further, and where we would rather integrate than rebuild.

PParitySSurpassDDifferentiatorIIntegrate
CapabilityClearstoryBuildertrendBuildxactChange Order Systems
T&M tickets and signaturesYesPartialPartial
PMobile and offline, signatures, geo and time evidence
Change request logYesYesYes
SRisk, value, aging and next-action intelligence
Labour, material and plant ratesYesYesYes
PContract-specific markups with provenance on every line
Client approvalYesYesYes
SStaged review, comments, partial approval, exact version evidence
Accounting and project integrationsHigher tierNative suiteNative suite
DSystem-neutral connector layer
Automated variation detectionLimited / import AINo public emphasisAI estimating
DContinuous scope-to-field variance detection
Notice complianceWorkflowGenericGeneric
DVersioned contract and jurisdiction notice clock with checklist
Dispute evidenceLogsDocumentsDocuments
DChronology, causation and cost evidence pack
Recovery analyticsReportingFinancial reportsCosting
DDetected-to-collected revenue funnel
Full construction managementNoYesYes
IWe do not rebuild it — we integrate with it

Competitor capabilities summarised from publicly published product information at the time of writing. Feature sets move; check current vendor documentation before making a decision on this table alone.

05Why the claims survive

Anyone can raise a claim. The question is whether it holds up eight months later.

These six properties are enforced by the system rather than by discipline, because discipline is the first thing to go when a job gets busy.

The deadline is arithmetic, not a guess

Detection proposes a classification. A person confirms it. Only then does the clock start, computed by day-counting over a frozen calendar and stored with the clause it came from. Recompute a deadline three years later and you get the same date.

A submission is bound to exact versions

Every issued claim carries a content hash over its notice, its cost build-up version and its full evidence manifest. Revise the price and the old version is superseded — a client decision cannot land on it unless they deliberately confirm they mean to.

Originals are immutable

Evidence is hashed on capture and never edited in place. Annotation and redaction create a derivative that records what it came from, so the file you relied on and the file somebody marked up both survive.

Cost and margin never leave the building

Commercial fields are stripped server-side for restricted roles and for every external reviewer. Nothing sensitive sits in the page waiting to be un-hidden.

Every decision is on a tamper-evident log

Each audit event carries the hash of the one before it. Remove or edit a single row and the chain breaks from that point forward, which is exactly the property an adjudicator cares about.

Attribution is kept honest

Platform-detected, platform-assisted and imported changes are separated everywhere, so nobody can claim credit — or charge a percentage — against work the engine did not surface.

06Commercial model

Priced against what it recovers, not what it costs to run.

Implementation runs A$2,000 to A$20,000 depending on project complexity, and includes the concierge setup and commercial review that make the first recovery happen rather than the first login.

Growth
A$399/month

A first crew running a limited number of active projects.

  • Limited active projects
  • Field capture, T&M tickets and signatures
  • Change register, pricing and notices
  • Notice clock and evidence packs
  • Email, CSV and cloud-drive ingestion
Start with a sprint
Promost subcontractors
A$999/month

The working plan for a subcontractor with real variation exposure.

  • Everything in Growth
  • Scope-to-field variance detection
  • Accounting and project integrations
  • Client approval portal
  • Portfolio analytics and recovery forecasting
  • Full audit chain and role-based commercial restrictions
Book a recovery sprint
Enterprise
A$2,500+/month

Multi-office and joint-venture structures with their own systems.

  • Everything in Pro
  • SSO and SCIM provisioning
  • ERP, scheduling and cost system connectors
  • Regional hosting and retention controls
  • Named support and implementation
Talk to us
Optional managed recovery service

For contractors who would rather hand the commercial work over, we can run the recovery cycle on your behalf. Percentage-based fees are only ever offered after legal, regulatory and attribution review — and only against work the detection engine actually surfaced, which is why origin is recorded on every change from the first minute.

Implementation
A$2,000 – A$20,000
By project complexity
07How an engagement starts

A paid recovery sprint, not a pilot that goes nowhere.

We do not go past Release 0 until five contractors have given us real project data, three of them are paying, aggregate open variation value exceeds A$500,000 and two have accepted at least A$999 a month after a proven recovery. That gate is ours, not yours.

Release 04–6 weeks

Paid recovery sprint

Project and scope import, mobile field events, T&M tickets and signatures, a manual change register, pricing, notices, a PDF evidence pack and the revenue dashboard — with concierge setup and a commercial review.

Exit criteria
Three contractors on live projects, at least 25 real events processed, and one billable change recovered or materially accelerated.
Release 18–10 weeks

Sellable platform

Contract rule review, the notice clock, email and document ingestion, the client approval portal, accounting sync, roles, billing, advanced reports and the complete audit trail.

Exit criteria
Contractors running the whole cycle themselves, without concierge support.
Release 210–16 weeks

10x intelligence

Scope variance detection, drawing revision signals, the schedule impact workspace, project management integrations, recovery forecasting, portfolio benchmarks and enterprise SSO.

Exit criteria
Detection carrying the majority of recovered value.
What this platform does not do

It does not determine legal entitlement, and it does not guarantee payment. It records the commercial position you take and the date you took it.

Jurisdictional and contract notice templates require qualified review before you rely on them. A rule built on an unapproved clause will not start a clock.

AI identifies and drafts. An authorised person approves every external notice, every price and every contractual assertion — nothing leaves the building on its own.

No unapproved change alters your source estimate, your contract or your accounting ledger. The platform is downstream of your systems of record, never on top of them.

Start where the money is

Bring us one project and six months of open variations.

In a four to six week sprint we load the contract, put your crews on field capture, and work the register with you until a real change is recovered or materially accelerated. If nothing moves, you will know quickly and cheaply.